title: "The Contract Lifecycle: Stage 4 – In Delivery"
description: This contract stage consists of listing and tracking contract activities and variations, then closing out when the contract work is completed.   This stage has three steps, listed as tabs across the t
---

[Skip to content](https://support.surepact.com/the-contract-lifecycle-stage-4-in-delivery-1#main-content)

English

Show submenu for translations

[Submit a ticket 🎫](https://support.surepact.com/kb-tickets/new?hsLang=en) [Customer portal](https://portal.surepact.com/tickets-view?hsLang=en)

![0224\_Surepact\_Logo-Primary-1.png\]](https://support.surepact.com/hs-fs/hubfs/0224_Surepact_Logo-Primary-1.png?height=43&name=0224_Surepact_Logo-Primary-1.png)

Open main navigation

Close main navigation

- English
  
  Show submenu for translations
- [Submit a ticket 🎫](https://support.surepact.com/kb-tickets/new)
- [Customer portal](https://portal.surepact.com/tickets-view)
- Visit our website!

 Visit our website!

 Hello. How can we help you?

- There are no suggestions because the search field is empty.

1. [SurePact | Knowledge Base](https://support.surepact.com/?hsLang=en)
2. [Projects & Contracts](https://support.surepact.com/projects-contracts?hsLang=en)
3. [Managing Contracts Within Projects](https://support.surepact.com/projects-contracts?hsLang=en#managing-contracts-within-projects)

# The Contract Lifecycle: Stage 4 – In Delivery

This contract stage consists of listing and tracking contract activities and variations, then closing out when the contract work is completed.

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875917709071-2.png)

 

This stage has three steps, listed as tabs across the top:

- [Step 1 – Delivery Tracking](https://support.surepact.com/the-contract-lifecycle-stage-4-in-delivery-1#DeliveryTracking)
- [Step 2 – Variations](https://support.surepact.com/the-contract-lifecycle-stage-4-in-delivery-1#Variartions)
- [Step 3 – In Delivery Closeout](https://support.surepact.com/the-contract-lifecycle-stage-4-in-delivery-1#InDeliveryCloseout)

 

### Step 1 – Delivery Tracking

This is the step where you create and track contract activity. For each section, be sure to keep track of completion dates and approvals as needed.

 

The first section of this step is [Planned Activities](https://support.surepact.com/planned-activities-1?hsLang=en), listing the “to do” items that need to be done in order to complete the contract work. 

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875917710479-2.png)

 

Next comes [Internal Deliveries](https://support.surepact.com/internal-deliveries-1?hsLang=en), covering deliverables such as freight, fuel, labour, materials, etc.

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875917711247-2.png)

 

The [Progress Claims](https://support.surepact.com/progress-claims-1?hsLang=en) table lists the associated costs involved with completing a milestone or planned activity. 

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875933082639-2.png)

 

Finally, the [Defects](https://support.surepact.com/defects-1?hsLang=en) table lists contractor errors or project deficiencies.

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875917712271-2.png)

 

 

### Step 2 – Variations

[Variations](https://support.surepact.com/variations-for-contracts-1?hsLang=en) are set up to resolve funding or timing differences between project realities and original agreements and schedules.

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875933084047-2.png)

There are three types of variations (EOT refers to Extension of Time): 

- **Price:** Differences in funding. Example: You need to change the scope which results in a price change.
- **Commencement EOT:** Differences in start times. Example: You need to start a delivery later than scheduled.
- **Delivery EOT:** Differences in end times. Example: A delivery will be completed later than scheduled

 

### Step 3 – In Delivery Closeout

When all deliveries and variations are complete, head over to the last step. 

Enter a note and click **Submit**.

![](https://support.surepact.com/hubfs/Knowledge%20Base%20Import/surepact.zendesk.comhcarticle_attachments8875933628047-2.png)

 

- [Getting Started (For All Users)](https://support.surepact.com/getting-started-for-all-users?hsLang=en)
- [Funding Programs (For Grantmakers)](https://support.surepact.com/funding-programs-for-grantmakers?hsLang=en#main-content)

    - [Creating & Managing Funding Programs](https://support.surepact.com/funding-programs-for-grantmakers?hsLang=en#creating-managing-funding-programs)
    - [Application Round(s) Setup](https://support.surepact.com/funding-programs-for-grantmakers?hsLang=en#application-rounds-setup)
    - [Application Review, Allocations, Funding Agreements](https://support.surepact.com/funding-programs-for-grantmakers?hsLang=en#application-review-allocations-funding-agreements)
    - [Program Delivery and Reporting](https://support.surepact.com/funding-programs-for-grantmakers?hsLang=en#program-delivery-and-reporting)
- [Funding Opportunities (For Applicants & Recipients)](https://support.surepact.com/funding-opportunities-for-applicants-recipients?hsLang=en#main-content)

    - [Applying for a Funding Opportunity](https://support.surepact.com/funding-opportunities-for-applicants-recipients?hsLang=en#applying-for-a-funding-opportunity)
    - [Tracking & Managing Applications](https://support.surepact.com/funding-opportunities-for-applicants-recipients?hsLang=en#tracking-managing-applications)
- [Grant Management & Reporting](https://support.surepact.com/grant-management-reporting?hsLang=en)
- [SurePact Records](https://support.surepact.com/surepact-records?hsLang=en)
- [Portfolios](https://support.surepact.com/portfolios?hsLang=en)
- [Projects & Contracts](https://support.surepact.com/projects-contracts?hsLang=en#main-content)

    - [Project Management](https://support.surepact.com/projects-contracts?hsLang=en#project-management)
    - [Managing Contracts Within Projects](https://support.surepact.com/projects-contracts?hsLang=en#managing-contracts-within-projects)
- [Risk, Compliance & Asset Management](https://support.surepact.com/risk-compliance-asset-management?hsLang=en#main-content)

    - [Risk & Issue Management](https://support.surepact.com/risk-compliance-asset-management?hsLang=en#risk-issue-management)
    - [Asset Management](https://support.surepact.com/risk-compliance-asset-management?hsLang=en#asset-management)
- [Administration & System Setup](https://support.surepact.com/administration-system-setup?hsLang=en#main-content)

    - [External Assessors](https://support.surepact.com/administration-system-setup?hsLang=en#external-assessors)
- [Common Processes](https://support.surepact.com/common-processes?hsLang=en)
- [Release Notes & Support](https://support.surepact.com/release-notes-support?hsLang=en#main-content)

    - [What's New in Version 6?](https://support.surepact.com/release-notes-support?hsLang=en#whats-new-in-version-6)
    - [What?! Version 7 Already?](https://support.surepact.com/release-notes-support?hsLang=en#what-version-7-already)
    - [Version 8, let's create!](https://support.surepact.com/release-notes-support?hsLang=en#version-8-lets-create)
- [External Assessor](https://support.surepact.com/external-assessor?hsLang=en)

[![Chill listening crop-3](https://support.surepact.com/hs-fs/hubfs/Logo%20-%20Favicon%2090x90%20(PNG%20Watermark)-1.png?width=35&height=35&name=Logo%20-%20Favicon%2090x90%20(PNG%20Watermark)-1.png "Chill listening crop-3")](https://surepact.com/)

SurePact | Knowledge Base

<https://www.linkedin.com/company/surepact/posts/?feedView=all> <https://www.youtube.com/@surepact>

Copyright © 2026, SurePact Pty Ltd